Status Zakończone
Zamawiający Tramwaje Śląskie i Miasto Katowice
Wartość zamówienia 31.2 mln PLN brutto
Realisation period 10/2013 - 06/2015

Modernization of the tramway embedded in the ul. Kościuszki roadway, from Al. Górnośląska to the railway overpass in Katowice. Reconstruction of the traction system (task No. 3), modernization of the final section of line Nos. 6 and 16 in Katowice Brynów (task No. 4)

within the investment project

"Modernization of tram and trolley bus infrastructure in the Upper Silesia Agglomeration, along with the accompanying infrastructure"

The contract is for reconstruction of the tramway along with the traction system along ul. Kościuszki , at the sections from the crossing with ul. Kochanowskiego to the railway overpass at Al. Górnośląska and from the crossing with ul. Słowików passing the crossing with ul. Huberta.

Civil construction works include:

  • Construction of a tramway
  • Construction of stop platforms
  • Reconstruction of the traction system
  • Control and heating of the rail points
  • Reconstruction of roads, sidewalks and crossings
  • Construction of a dewatering system, sewerage system, gas system, power supply equipment and road lighting