Powstańców Śląskich – the next stage completed

On December 22, 2014, tram traffic was restored on the route between the terminuses at Koło and Nowe Bemowo. At the same time, on December 21, 2014, works which enable the operation of the entire tramway, connecting ul. Górczewska and ul. Radiowa, were completed. The procedure to obtain the permit to operate the tramway is on-going, and once it is obtained the section will be opened.

 

Over a period of nearly 6 months:

  1. the following was built:

  • 5,230.20 track meters of tram trackbed in three systems: Rheda City, Rheda green trackbed and classic track

  • 12 332.19 track meters of catenary,

  • 30 840.00 m of supply cables,

  • 10 tram platforms along with utilities, lighting and passenger information system,

  • traffic lights at 6 junctions

  • an additional section of the western carriageway of ul. Powstańców Śląskich between ul. Dywizjonu 303 and ul. Pirenejska.

 

  1. The following were reconstructed and removed:

  • 73 sewage system and water supply line conflicts,

  • 79 power conflicts,

  • 12 telecommunications conflicts,

  • 5 gas conflicts,

In spring 2015 roadworks and finishing works will be completed.

 